Scope of work
Replaced obsolete process-control PLCs with a redundant architecture and moved emergency and interlock shutdown onto a new, dedicated Safety Instrumented System (SIS) designed in line with IEC 61508 and API RP 1004. Added surge protection to the terminal automation system's PLC I/O and a redundant fibre backbone between the control room and the substation.
Challenge
The terminals had to keep loading trucks. The old Allen-Bradley PLC-5 controllers, in the control room and out at the substation, were replaced with redundant ControlLogix controllers while all existing field wiring stayed in place. About 5,000 I/O across the three sites were cut over to a written transition plan, each terminal changing over in a single 8-hour window, all bays at once rather than bay by bay.
Result
Delivered on time within the planned windows. With safety shutdown separated from process control, the terminals run on a more stable system with less risk of an unplanned stop in loading.