Scope of work
Fabricated and installed cable-duct and conduit supports, then pulled three 22 kV power cables over a 3 km route to supply a new storage terminal.
Challenge
3 km in only 40 days, along a route crossing several working areas of the complex. Each area needed its own work permit, so materials, equipment and crews were staged area by area to keep to the plan.
Result
Handed over on time, so the owner could energise at 22 kV and start testing the new plant on schedule.